How Can We Help?

How to enter work order trigger?

You are here:
< Back
  1. Proceed to Meter > Meter List 
  2. Select any meter and click Work Order Trigger button
  3. User able to insert their expected reading for next maintenance
  4. User can set the condition when the meter will be triggered
    • Either One time or Every time it reaches the value
    • By entering the value Trigger when
        • Options include less than, equal to and greater than 
        • User must insert a value for the selected condition
  5. User able to select checklist from template or manually insert checklist for the PIC to use once the meter is triggered
  6. Once the meter trigger is set, the triggered reading will be highlighted in red in the Reading List and automatically generate a preventive work order

Share This
Scroll to Top